Project Milestones & Phases

  • The Planning phase involves preparation for RFP, team selection and High level requirements. This phase started in May 2023.
  • The Procurement phase involves request for proposals, technology budget, vendor selection, and contract negotiations. This phase started in November 2023 and ends in March 2024.
  • The Discovery phase involves determining detailed requirements and ensure common understanding. This phase starts in April 2024 and ends in July 2024.
  • The Configuration phase involves Software configured to meet requirements. This phase starts in June 2024 and ends in October 2024.
  • The Testing & Training phase involves Configuration tested and compared to requirements and Users trained using multiple formats. This phase starts in July 2024 and ends in December 2024.
  • The software will Go Live in Jan 2025.